These are some contractor guidelines to the installation of tar snakes.
SEALING EXISTING PAVEMENT CRACKS AND JOINTS: 7 1 95
Description of Work:
The work covered by this provision consists of sealing existing longitudinal and transverse pavement cracks and joints with Sealant Type 2, PS/AR (hot poured rubber asphalt) at locations as directed by the Engineer. The Contractor will not be required to seal the existing edge joints.
Materials:
Use Sealant Type 2, PS/AR (hot poured rubber asphalt) meeting the requirements of Article 1028 2 of the Standard Specifications.
Construction Methods:
Install the sealant so that it forms a complete watertight bond with a high degree of elasticity, with maximum flexibility and longevity under extreme temperature ranges.
Use a HCA (hot compressed air) lance at all times to blast out any vegetation, dirt, dampness and loose materials from the cracks and joints.
Use a concentrated hot air jet that is a minimum of 3000°F (1649°C) in temperature and that has a minimum air jet force of 3000 feet per second (914.4 meters per second) of blasting.
Force open asphalt cracks and joints, clean warm and dry, and have ready for the application of the preheated sealant for maximum crack sealability.
Preheat the sealant to correct temperature, using the air jacketed flow method to prevent the burning of the modified rubber in the sealant. Perform this by means of a trailer mounted 190 gallon (719.2 liter) safety tested crack sealant preheater melter kettle, with a horizontally mounted full sweep double paddle agitator.
Apply sealant in the prepared cracks and joints at a temperature range of 370°F (188°C) minimum and 420°F (216°C) maximum, using the pressure screed shoe to completely fill the crack and joint, leaving a sealed 2" (50.8 mm) overband. Excessive overbanding or waste of sealant materials will not be tolerated.
Do not apply the PS/AR sealant when the surface temperature of the pavement is below 32°F (0°C).
All cracks and joints sealed must have a minimum of 1/8" (3.2 mm) depth of sealant installed.
After the crack and joint has been sealed, promptly remove any surplus sealer on the pavement. Do not permit traffic over the sealed cracks and joints without approval by the Engineer.
The sealant is to be packaged in polyethylene bags and placed in boxes that weigh approximately 60 pounds (27.2 kg). The sealant may be packed in 60 pound (27.2 kg) boxes containing two polyethylene bags of sealant which weigh approximately 30 pounds (13.6 kg) each. Boxes of sealant are to be palletized for shipment. The pallets are to be protected with a weatherproof covering. The Contractor is responsible for storage.
Method of Measurement:
The amount of the sealant material to be paid for will be the actual number of pounds (kg) of material that has satisfactorily been used to seal pavement cracks and joints in the designated highway. Any material that has been spilled, used in excessive overbanding, wasted, misapplied, or unsatisfactorily used in any way will be deducted in determining quantities for payment. The Engineer will determine the quantity, if any, to be deducted. The Engineer's decision on the quantity to be deducted will be final and binding.
Basis of Payment:
The quantity of sealant material, measured as provided above, will be paid for at the contract unit price per pound (kg) for "Sealing Existing Pavement Cracks and Joints". The above price and payment will be full compensation for all work required to seal the pavement cracks and joints including but not limited to furnishing, hauling, loading and unloading, and storage of all sealant materials; cleaning and preparation of cracks and joints to be sealed; application of sealant material in the prepared cracks and joints; any clean up; and any incidentals necessary to satisfactorily complete the work.
SP6R55
Payment will be made under:
Sealing Existing Pavement Cracks and Joints Pound (kg)
And here is some terminology used in roadway maintenance and repair.
Aggregate - A substance composed of mineral crystals or mineral rock fragments, used in pavement.
Alligator Cracking (or fatigue cracking
) - Cracks in an asphalt pavement surface forming a pattern that
resembles an alligator’s hide or chicken wire. Alligator cracking may
begin with a single longitudinal crack in the wheel path. The cracks
indicate failure of the surface layer generally caused by repeated
traffic loadings.
Average Daily Traffic Counts - The average number of vehicles using a roadway in one day.
Bitumen
- Mixtures of hydrocarbons (for example tar) occurring naturally or
man-made from coal or petroleum. Used for surfacing roads and for
waterproofing.
Bituminous - Of or pertaining to bitumen.
Bituminous asphalt/blacktop/pavement - A pavement comprising layers of aggregate mixed with a bituminous binder, such as asphalt, coal tars, and natural tars.
Business Loop (BL) –
A business loop is a surface route that leads into a downtown business
district and returns to the freeway at the other end. Frequently, the
business loop is the alignment of the original highway before that
highway was bypassed. (See Business Route.)
Boulevard (BLVD) -
A wide street with a landscaped center island running the length of the
street. Boulevards are usually found in urbanized areas.
Business Route (BR) -
A business route connects the freeway or through highway with the
downtown and commercial areas of a city or town. Business routes are
primary arterials and begin and end on the Interstate. Business Loops
and Business Spurs are types of Business Routes. Business Loop implies
that the business route will return to the parent route, while a
business spur implies that the business route will only spur into the
commercial area and not return to the parent route.
Business Spur
- A business spur is a surface street route leading from the Interstate
highway into the central commercial district. The spur route ends upon
reaching a specified point within that urban area. (See Business Route.)
Capital Preventive Maintenance
- Plan for cost-effective treatments to an existing road system that
preserves or improves the condition of the system without
(significantly) increasing structural capacity.
Check Station - See weight station.
Chip Seal
- A surface treatment in which the pavement is sprayed with asphalt
(generally emulsified) and then immediately covered with aggregate and
rolled. Chip seals are used primarily to seal the surface of a pavement
with non load-associated cracks and to improve surface friction. This
is typically used to extend the life of the pavement surface by sealing
out moisture, which can cause major damage to pavement, until major
repairs are made.
Cold Mill
– Removal of pavement material from the surface of the pavement either
to prepare the surface to receive overlays (by removing rutting and
surface irregularities) or to restore pavement to the correct
specifications. This process is also used to remove oxidized asphalt
concrete.
Conflict
– Traffic conflicts occur when vehicles moving in different directions
interfere with each other, i.e., merging, diverging and crossing.
Context Sensitive Solutions: MDOT works with communities to identify local transportation needs, taking into account statewide priorities, including the Statewide Long Range Plan, the Five Year Program,
and the environment impact. Context Sensitive Solutions encourages
early and continuous involvement in the planning process so the final
result is both an asset to the community and sensitive to community and
environmental concerns.
Continuous Traffic Flow - A steady, unbroken stream of traffic.
Controller - An electrical mechanism for controlling traffic signal operation which is mounted in a cabinet.
Crack -
A fracture of the pavement surface not necessarily extending through
the entire thickness of the pavement. Cracks generally develop after
initial construction of the pavement and may be caused by temperature
changes, excess loadings, or excess deflections, which are movements in
or under the pavement. (See Working Crack.)
Crack Filling
- Placing materials into non-working cracks to reduce the infiltration
of water and other matter, while also reinforcing the adjacent
pavement. Crack filling should be distinguished from crack sealing (see
below).
Crack Sealing
- Placing specialized materials into working cracks in unique
configurations to keep water and other matter out of the crack and the
underlying pavement layers. (See Working Crack.)
Crash Potential - The relative degree of safety of a location or area.
Cure
- A period of time following placement and finishing of a material such
as concrete during which desirable engineering properties (such as
strength) develop. Improved properties may be achieved by controlling
temperature or humidity during curing.
Curing
- The maintenance of a satisfactory moisture content and temperature in
concrete during its early stages so that desired properties may develop.
Delineators - Road markers that define lanes and shoulders; safety measures intended to guide drivers.
Diamond Grinding
- A process that uses a series of diamond-tipped saw blades mounted on
a shaft to shave the upper surface of a pavement to remove bumps,
restore pavement rideability, and improve surface friction.
Dowel
- A plain round steel bar which extends into two adjoining slabs of
pavement at a joint. Dowels are used to keep concrete slabs from
heaving up and down.
Dowel Bar Retrofits
- A rehabilitation technique used to distribute the weight of vehicles
across existing joined pavements by placing dowel bars across joints
and/or cracks.
Downstream - Points on a route further ahead in the direction of traffic flow.
Driver Response – Driver reaction to a message or condition on a highway such as a sign or traffic signal.
Efficient Systems - A route or network of routes on which traffic flows with minimum delay and congestion.
Emulsified Asphalt - A liquid mixture of asphalt binder, water and an emulsifying agent.
Freeway -
A freeway is an access-controlled, divided highway designed for the
unimpeded movement of large volumes of traffic. Characteristics of a
freeway include controlled access through the use of interchanges, and
use of underpasses or overpasses at intersections.
Frost Heave - A process in which the ground freezes and thaws, creating potholes.
Gaps - Breaks in the traffic stream long enough to permit vehicles or pedestrians access across or into the traffic stream.
Gore - The V-shaped area that separates through-traffic from exiting or entering traffic on freeways and highways.
Grade Separation - A crossing that uses an underpass or overpass to eliminate conflict points.
Grooving
- The process used to cut slots into a pavement surface to provide
channels for water to escape beneath tires. This improves skid
resistance and reduces the potential for hydroplaning.
Highway (HWY) -
A main road that provides direct access to buildings and intersections.
Unlike a limited access freeway, a highway has intersections at grade
level and signs and signals to control traffic.
Hot Mix Asphalt Concrete (HMAC or HMA)
- A carefully controlled mixture of asphalt binder and well-graded,
high quality aggregate thoroughly compacted into a uniform density.
HMAC pavements may also contain additives such as anti-stripping agents
and polymers.
Interchange
- An interchange is the junction of a freeway and another road.
Interchanges keep the traffic flowing on the freeway, but there may be
some restrictions on the connecting routes. A complete interchange
provides for movements in all directions; a partial interchange has
some missing connections.
Lane Miles
- The number of miles of pavement going in one direction on any given
road. Miles of roadway x (times) number of lanes = lane miles.
Law Observance Study – A survey designed to check effectiveness of various traffic control devices.
Limited Access
- A highway or section of highway designed for travel by registered
motor vehicles. Access is limited to intersections, and driveways are
generally not allowed. Freeways are a common type of limited access
highway.
Load Transfer
- The ability to distribute the weight of vehicles across joined
sections of pavement. This is a critical factor in extending pavement
life.
Median - A barrier, constructed of concrete, asphalt, or landscaping, that separates two directions of traffic.
Microsurfacing
- A mixture of polymer-modified asphalt emulsion, mineral aggregate,
mineral filler, water, and other additives, properly proportioned,
mixed, and spread on a paved surface. Unlike slurry seal,
microsurfacing can be used on high volume roadways to correct wheel
path rutting and provide a skid resistant pavement surface.
Milling - Grinding off the top layer of pavement.
Noise Wall - See Sound Wall
Overbanding
- Overfilling of a joint or crack reservoir so that a thin layer of
crack or joint sealant is spread onto the pavement surface over the
joint or crack.
Patch - Repair of a localized defect in the pavement surface.
Pavement miles - The number of miles of pavement in both directions of a road/freeway.
Pavement Preventive Maintenance
- Planned strategy of cost-effective treatments to an existing roadway
system to extend the life of the pavement, retard future deterioration,
and maintain or improve the functional condition of the system (without
increasing the structural capacity).
Pavement Reconstruction – Complete removal and replacement of the existing pavement structure and may include new and/or recycled materials.
Pavement Rehabilitation
- Structural enhancements that extend the service life of an existing
pavement and/or improve its load carrying capability. Rehabilitation
techniques include restoration treatments and structural overlays.
Performance Period - Period of time that a newly constructed or rehabilitated pavement structure will perform before deteriorating.
Platoon - A group of vehicles moving, more or less as a unit, along a signalized roadway system.
Potholes – A hole in the pavement surface- commonly caused by moisture.
Preserve -
A project type involving rehabilitation of existing roadways and may
include resurfacing or reconstruction of existing roads and bridges.
Profilameter - A computer-aided device used to measure the smoothness of the road.
Progressive Movement - Traffic moving at a constant speed with a minimum number of stops.
Reconstruct - A term used to describe a road project where the roadway is taken down to its base whereby necessary repairs can be made.
Retrofit Dowel Bars
- Dowels that are installed into slots cut into the surface of an
existing concrete pavement to distribute the weight of vehicles across
existing joined pavements.
Rideability - A measure of the ride quality of a pavement as perceived by its users or roughness measuring equipment (See profilameter).
Right-of-Way (ROW) - Land and/or property acquired for or devoted to transportation purposes. Right-of-way is also a project phase.
Right-of-Way Assignment - The "green" phase of a stop-and-go signal when a certain movement of traffic is permitted to flow.
Route Miles - The number of miles a car travels to get from point A to point B.
Roundabout- See Traffic Circle.
Rubblize - A process where concrete is broken up into uniform size pieces, rolled flat and covered with a new surface (usually asphalt).
Sandblasting
- A procedure in which compressed air is used to blow sand particles at
a pavement surface to abrade and clean the surface. Sandblasting is a
construction step in partial-depth patching and joint resealing.
Sand Seal
- An application of asphalt binder, normally an emulsion, covered with
a fine aggregate. It is used to improve the skid resistance of slippery
pavements and to seal against air and water intrusion.
Scoping - The process of determining the type and size of a proposed project.
Seal Coats - See Surface Treatment
Sealant
- A material that has adhesive and cohesive properties to seal joints,
cracks or other various openings against the entrance or passage of
water or other debris in pavements.
Sealing
- The process of placing sealant material in prepared joints or cracks
to minimize intrusion of water and incompressible materials. This term
is also used to describe the application of pavement surface treatments.
Signal Cycle - The time required for all phases of a signal to take place - from beginning of green to beginning of green.
Signal Warrants - A set of guidelines designed to determine the need for a stop-and-go traffic signal.
Single-Point Urban Interchange (SPUI)
- A single-point urban interchange is a variant on the standard diamond
interchange, whereby all traffic meets at one single traffic signal in
the center of the bridge over the freeway (or underneath the freeway).
These interchanges can accommodate more traffic in smaller spaces,
hence their appeal in urban areas.
Slurry - Mixture of a liquid and fine solid particle that together are denser than water.
Slurry Seal
- A mixture of slow setting emulsified asphalt, well graded fine
aggregate, mineral filler and water. It is used to fill cracks and seal
areas of old pavement, to restore a uniform surface texture, to seal
the surface to prevent moisture and air intrusion into the pavement,
and to improve skid resistance.
Sound Wall - (Also called Noise Wall) A structure built alongside a roadway to reduce vehicular noise in nearby neighborhoods.
Spalling, Sliver - Chipping of concrete edge along a joint sealant usually within 12 millimeters of the joint edge.
Spalling, Surface - Cracking, breaking, chipping, or fraying of slab surface, usually within a confined area less than 0.5 square meters.
Speed Checks - Radar studies conducted to obtain information concerning the distribution of vehicle speeds through an area.
Speed Study - The speed study determines the 85th percentile speed at that location. This means 85% of the motorists are driving at or below this speed.
State Trunk Line -
This network of road types (Interstate, Michigan and U.S. routes)
supports the state's commercial activities. An important element in the
state's economy, it connects commercial and manufacturing areas and
enables goods to be moved across the state.
Streetscape -
Equipment, such as lights, plant material or benches placed off the
street to improve or enhance the appearance and usability of a street.
Superstructure - A bridge.
Surface Seal - See surface treatment.
Surface Treatment
- (Also called surface seals, seal coats or chip seals) Any material
applied to asphalt pavement to restore or protect the surface. Surface
treatments are typically less than 25 millimeters thick.
Thin Overlay - A Hot Mix Asphalt (HMA) overlay of 38 millimeters (1.5 inches) or less.
Timing Permit
- A form indicating/authorizing how a traffic signal will operate; when
it will flash, how much "green time" will be allotted to each leg of
the intersection, how it will operate in relation to adjacent signals,
and what special provisions will be made for high-volume, peak-hour
traffic.
Tine - To create grooves in the pavement for traction.
Traffic Calming
- A set of street designs and traffic rules that slow and reduce
traffic while encouraging walkers and cyclists to share the street.
Traffic calming measures include: traffic circles, raised crosswalks,
sidewalk extensions speed humps and medians.
Traffic Circle
- An intersection where traffic moves around a circular center island.
Some traffic circles have traffic signals. Also called a roundabout.
Traffic Engineer - An experienced engineer specializing in issues associated with the safe and efficient operation of roadway facilities.
Traffic Volumes - The actual number of vehicles passing a given point.
Transportation Economic Development Fund (TEDF)
- The TEDF is a fund that provides a means for state government, local
agencies and businesses to work together on highway, road, and street
projects that support economic growth. It was enacted by the Michigan
State Legislature in 1987.
Transportation Enhancement Funds -
Also known as the Transportation Enhancement Activity Fund. This
federal fund sets aside a portion of Surface Transportation Funds (STP)
specifically for landscaping and street improvements, bike and foot
paths, mitigating highway runoff and the historic preservation of
transportation-related structures.
Uniform Standards - A policy of consistent traffic control devices on all roadway systems throughout the nation.
Urban Area -
An urban area is a designation defined by the U.S. Bureau of the Census
as an area located outside of an urbanized area with a population over
5,000.
Urbanized Area -
An area containing a city or twin cities of 50,000 or more people
surrounded by a closely settled incorporated area which also meets
specified criteria of population and density.
U.S. Routes - Non-interstate federal highways.
Weigh Station
– (Also called Check Station.) A weigh station is a set of scales
located alongside a freeway that verifies that trucks and buses are
within the legal weight limit.
Working Crack
- A crack in a pavement that changes, becoming narrower or wider under
different temperature conditions. A working crack develops through
movement in or under the pavement, for example, when an old expansion
joint fails.